Original caption
In commercial construction, know your contract before you bring in another trade to finish a subcontractor’s scope. If a trade is falling behind because they can’t staff the job, didn’t order materials on time, or are prioritizing other projects, your contract may give you options… but you need to follow its requirements. Make sure they’ve received the required notice and opportunity to address the issue. And check that they aren’t waiting on something from your team, such as an answered RFI, an approved change order, or a payment issue. If you don’t have your documentation and process in order, you may not be able to recover the cost through a backcharge. Want to learn more about construction project management? Click the link in my bio. #ConstructionManagement #CommercialConstruction #ProjectManagement #ConstructionTips #Backcharges